According to the Agency’s source, at present, the runway number two is 90% completed. A total construction readiness of the airfield’s facilities is 84,5%. Currently, 235 builders and 67 items of building and road machinery are engaged in the construction works at the site.
Apart from construction of a new runway, the main taxi track is being extended and a number of other taxi tracks are under construction.
Construction works are scheduled to be completed by the end of the year.