DataLife Engine / First stage of Rosatom’s object construction completed in Nizhny Novgorod region

First stage of Rosatom’s object construction completed in Nizhny Novgorod region

As Construction.RU was told today by the press office of the Federal Special Construction Agency of Russia, the foundation work of the object’s main building has been finished, cast-in-situ walls have been erected and metal structures of inner and external frame have been installed.

At present, metal structures of walls and roofing, as well as partition and separation walls are being mounted.

Builders are mounting inner and external utility networks and communications, installing high voltage power lines.

A range of works regarding landscaping, road building and site buildup are to be implemented yet.

9-01-2017, 15:14
Вернуться назад