“Construction has stepped over its equator. Almost 55% of the total volume of works is performed,” Mr. Novikov announced at the Crimean transport forum in Alushta.
Construction is underway in two areas: a road and railway one. By the end of June, 81% of piles have been driven, 56% of pillars installed and 27% of superstructures assembled.
Earlier, during the Direct Line with President, Vladimir Putin stressed that the Kerch Strait bridge would be completed in time.