A powerful electricity transmission line has been put in operation in Datka-Kemin in Kirghizia

logo russianconstruction.com
A powerful electricity transmission line has been put in operation in Datka-Kemin in Kirghizia
Tags: Photo source:

The construction of an electricity transmission line in Datka-Kemin has been completed.




As the press office of JSC “National electric networks of Kyrgyzstan” (NENK) told Construction.ru, work at the construction site has been completed. The working commission of NENK has accepted the work. State commissioning is now being carried out. The prime contractor of the Chinese energy construction company ‘Tebian Electric Apparatus Stock Co. Ltd.’ earlier advised the customer on the completion of work on the ETL “Datka-Kemin”(500kW capacity) and the “Kemin” substation (500 kW capacity).
The “ETL “Datka-Kemin”(500kW capacity) project and the “Kemin” (500kW capacity) substation includes the construction of the 405km long, 500kW overhead power transmission line and the 500kW “Kemin” substation, with the additional installation of autotype transformers with a capacity of 501kW each.
2 autotype transformers at the substation “Ala-Archa” are also being replaced, and operating and technological communication systems are being reconstructed. The contract is worth about $390m in total.