A tender is announced in Samara for the Alabinskaya metro station construction to be completed for 965.4 m roubles
As it is said in the competition documents published on the state procurement website, all work is to be complete by December 20th, 2017.
This year financing of 235 m roubles is planned, and 730.4 m roubles will be allotted in 2017.
Last year, the construction of the «Samarskaya - Alabinskaya” main line tunnel, architectural and finishing work of the “Rossiyskaya - Alabinskaya” tunnel, tunnel water lines laying, external supply lines installation and finishing work were assessed as much as 988 m roubles from the budget
The “Volgatransstroy